How to Plan a Full House Internal Demolition in Queensland: A Homeowner’s Guide

Planning a full house internal demolition comes down to settling five things before any work starts: exactly what is coming out and what is staying, whether any of it is structural, whether the house contains asbestos, who needs to be licensed for each part of the job, and where you and the waste will go while it happens. Get those five right and the demolition itself becomes the most predictable part of the renovation. Leave them open and they become the delays, the variations and the surprise costs.

This guide walks Queensland homeowners through each of those decisions in the order they need to be made. It is written for anyone stripping a whole house back for a major renovation, whether that is a post-war Brisbane home or a Gold Coast family house that needs a new kitchen, bathrooms and floors all at once. If you are only renovating one room, our guide to preparing your home for an internal strip-out covers the room-by-room preparation in detail.

What is a full house internal demolition?

A full house internal demolition strips the inside of a home back so the renovation can start from a clean slate. The house stays standing. The roof, external walls and structure remain, while the interior finishes and fittings are removed.

Depending on the renovation plan, that typically includes kitchens, bathrooms and laundries, floor coverings such as carpet, tiles, vinyl and floating floors, wall and ceiling linings, built-in wardrobes and joinery, and non-structural internal walls. What it does not include is anything that holds the house up. Changes to the structure are building work that needs its own design, approval and builder, and they sit alongside the demolition rather than inside it.

Spotless Demolition specialises in this internal work, from single rooms to whole houses, across residential demolition on the Gold Coast and Brisbane.

Where should you start planning?

Start with the finished renovation, not the demolition. The demolition scope should be written to suit the new design, so the plans from your builder, designer or architect come first. A demolition scope written before the design is settled tends to remove too much, or too little, and both cost money.

Once the design is clear, turn it into a written demolition scope. That document becomes the brief for quotes, the checklist on the day, and the reference point if anything is disputed later. It should list every room, what is being removed from each, what is staying, and anything that needs special handling.

What is coming out, and what is staying?

Walk the house room by room and make a decision on every item. The table below is a starting point for the conversation with your builder and your demolition contractor.

AreaCommonly removedDecide before demolition
KitchenCabinetry, benchtops, splashbacks, sink, appliances, tilingAppliances to keep or sell; whether benchtops are engineered stone
Bathrooms and ensuitesVanities, toilets, showers, baths, wall and floor tiles, screensFittings to salvage; where plumbing will be capped
LaundryTubs, cabinetry, tilingMachines to relocate or remove
FloorsCarpet, vinyl, floating floors, tilesWhether original timber floors under coverings are being kept
Walls and ceilingsLinings, non-structural partitions, cornicesWhich walls are structural; any feature walls or cornices to keep
JoineryBuilt-in wardrobes, linen presses, shelvingItems to reuse in the new layout

 

Original hardwood floors are the classic example of why this matters. In many older Queensland homes they sit under carpet or vinyl, and whether they are being restored changes how the coverings above them are removed and how the floor is protected for the rest of the job. Label anything you are keeping, and photograph it, so there is no confusion on the day.

Is any of it structural?

This is the question that most often changes the plan. Internal walls can be load-bearing, carrying roof or floor loads down to the footings, and some walls provide bracing even where they do not appear to carry much weight. You cannot reliably tell which is which by looking.

In Queensland, removing or altering a load-bearing part of a building generally requires building approval, which is issued by a building certifier. Your builder or designer should confirm with a structural engineer which walls can be removed and what support needs to go in their place. The demolition contractor then removes the non-structural elements, and the structural changes are handled as building work under that approval. Our guide to when you need a demolition permit on the Gold Coast or in Brisbane explains the approval side in more detail.

If you live in a unit or townhouse, also check your body corporate rules before the scope is finalised. Work that affects common property, shared services or the building’s structure usually needs body corporate approval as well.

Does your home contain asbestos?

If your house was built before 1990, there is a good chance it contains some asbestos. The Queensland Building and Construction Commission also notes that some houses built in the 1990s and early 2000s still used asbestos-containing products until the total ban came into effect in 2003. A full internal demolition disturbs exactly the materials where it tends to be found, so this check is not optional.

In Queensland homes, asbestos-containing materials can turn up in fibro wall and ceiling sheeting, particularly in older bathrooms and laundries, in eaves and gables, and in the backing of some old vinyl floor coverings. You cannot tell whether a material contains asbestos just by looking at it.

Build this into your plan in three steps:

  • Identify it early. Have suspect materials assessed by a licensed asbestos assessor or tested by a NATA-accredited laboratory before you book the demolition.
  • Remove it first. Any asbestos in the area being demolished needs to be removed under the asbestos rules before general demolition begins. Licensed removal work has its own notification requirements, so it needs lead time.
  • Do not disturb it yourself. Do not drill, cut, sand or break suspect materials while you are preparing the house. Leave them in place and point them out at the inspection.

Spotless Demolition offers asbestos removal alongside internal demolition, and we will talk you through what any test results mean for your job at the inspection.

Who needs to be licensed for each part of the job?

A full internal demolition usually involves several trades, and each has its own licensing. In Queensland:

  • Building work. A contractor must hold an appropriate licence from the Queensland Building and Construction Commission (QBCC) to contract for building work valued over $3,300. A written contract is also a legal requirement for work above that value, and the QBCC publishes a Contract for Demolition of Residential Premises for domestic demolition.
  • Plumbing and drainage. Plumbing and drainage work must be done by a licensed plumber whatever its value, including capping and making safe the existing services.
  • Disconnecting and making safe electrical circuits must be done by a licensed electrician.
  • Asbestos removal. Asbestos removal is licensed separately, by Workplace Health and Safety Queensland.

Ask every contractor for their licence numbers and check them yourself. The QBCC has a free online licence search, and Workplace Health and Safety Queensland publishes information on licensed asbestos removalists. A few minutes of checking is the simplest protection you have.

What happens to the power, water and gas?

Services need to be made safe before demolition starts, not during it. Before the crew arrives, your licensed electrician, plumber and, if needed, gas fitter should disconnect and cap the services in the areas being stripped out, in line with where they will be needed in the new layout.

Two practical points are worth planning for. First, the demolition crew and the trades who follow will usually need temporary power on site, so talk to your electrician about how that will be provided. Second, think about where services will be capped. Capping them in positions that suit the new design saves the next trades from undoing work that has just been done.

Can you live in the house during a full internal demolition?

For a full house, it is rarely practical. Once the kitchen and bathrooms are removed, the house has no working wet areas. Power and water are disconnected in parts of the house for stretches of the job. Even with good dust control, the house is a work site, with noise, open floors and constant movement of materials and equipment, which is not a safe place for children or pets.

Most homeowners plan to stay elsewhere for the demolition and the early stages of the rebuild. Book that accommodation with a buffer, because renovation timelines tend to move, and organise storage for the belongings that will not fit. Your furniture and personal items need to be out before the demolition starts. Our guide to clearing years of clutter before a renovation can help with that stage.

What does the demolition sequence look like?

Knowing the typical order of a professional internal demolition helps you plan your own tasks around it. Every job is different, but a well-run full house strip-out generally follows this sequence:

  • The house is cleared of contents and personal belongings.
  • Any asbestos identified in the scope is removed under the asbestos rules.
  • Licensed trades disconnect and make safe the services.
  • Items and areas that are staying, such as floors being kept, are protected.
  • Fixtures, fittings and joinery are removed room by room.
  • Floor coverings, wall and ceiling linings and non-structural walls come out.
  • Waste is removed throughout the job, not just at the end.
  • The house is cleaned and handed over, ready for the builder.

Dust control runs through every stage. Containment, negative air machines with HEPA filtration and wet methods keep dust inside the work area and away from neighbouring homes. Our guide to construction dust rules in Queensland explains why that matters.

Where does all the waste go?

A full house internal demolition produces more waste than most homeowners expect, and it is mixed: tiles, plasterboard, timber, cabinetry, carpet, metal and general rubbish. Some of it can be recycled if it is separated, and some of it, such as asbestos, is regulated waste with strict disposal rules.

Plan who is responsible for waste before the job starts, and where it is going. If you are on the Gold Coast and weighing up whether to handle some of it yourself, our guide to renovation rubbish removal and Gold Coast council rules covers tip fees, skip bins, asbestos disposal and what counts as illegal dumping. Spotless Demolition removes demolition waste as part of the job, so it leaves the site as the work progresses rather than piling up in the yard.

What about neighbours, noise and access?

Under Queensland’s Environmental Protection Act 1994, building work that makes audible noise is restricted to 6:30am to 6:30pm, Monday to Saturday, with no audible building work permitted on Sundays or public holidays. A demolition will be planned around those hours.

A short note to your neighbours before the job starts goes a long way. Let them know the dates, the working hours and who to contact. Make sure there is clear access for trucks and equipment, keep the driveway free on demolition days, and remember that placing a skip bin or materials on the road or footpath usually needs a council permit.

Full house internal demolition planning checklist

  • Finalise the renovation design before writing the demolition scope
  • Write a room-by-room scope listing what is removed and what stays
  • Confirm which walls are structural with your builder and engineer
  • Check whether building approval or body corporate approval is needed
  • Have suspect materials tested for asbestos and schedule any removal first
  • Check QBCC and asbestos licences for every contractor
  • Arrange disconnection of services by licensed trades
  • Organise accommodation and storage for the duration
  • Agree who handles waste and where it goes
  • Let your neighbours know the dates and working hours

Quick answers

Do I need council approval for an internal demolition in Queensland?

Not always. Removing non-structural fixtures, fittings and linings generally does not need building approval, but removing or altering a load-bearing part of the house does, and that approval comes from a building certifier. Confirm what is structural before the scope is locked in.

Can I stay in the house during a full internal demolition?

It is rarely practical. A full internal demolition removes the kitchen and bathrooms, services are disconnected for parts of the job, and the house becomes a work site. Most homeowners plan to stay elsewhere for the demolition and the early stages of the rebuild.

How do I know if my house has asbestos?

You cannot tell by looking. If your house was built before 1990, there is a good chance it contains some asbestos. Have suspect materials tested by a licensed asbestos assessor or a NATA-accredited laboratory before demolition is scheduled.

Does my demolition contractor need a QBCC licence?

In Queensland, a contractor must hold an appropriate QBCC licence to contract for building work valued over $3,300, and a written contract is required above that value. Asbestos removal is licensed separately by Workplace Health and Safety Queensland. Check licence numbers before you sign.